Hi All,
I have a problem with monitoring historical assigning schedule numbers line from material document. I mean that when we posting GR then it is connected somehow with schedule agreement and later on with specific schedule line. But where I can check that information for historical data. I looked for example in transaction ME33L but there is only information about connection between material document and position of schedule agreement and no further info for schedule line number.
Anyone knows something about that?
Best regards
Tomasz
Hi,
During GR, you are referring the PO / scheduling agreement number only, not schedule line number. So you cant find a link between schedukle line and the GR document number directly, as of my knowledge. You can find in EKET table against the schedule line the GR quantity, but the material document number is not available.
However, you can extract the dat with BW. Pls check the link below.
http://help.sap.com/saphelp_sm40/helpdata/en/69/063f3f2615e07fe10000000a114084/content.htm
Hope its helpful.
Regards,
AKPT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.