Strategy profile assignment

rahulakshay
Explorer
0 Kudos

I am PP/APO Guy -I have a location and product - I also have a strategy profile - In which screen (in which Tcode) do i assign/set  Loc-prod-resources against a strategy profile 

i could see strategy profile in multiple places , there should always be Global level and local level - in which screen strategy profile is assigned at Global level and in which screen at local level ?

When a run is conducted which takes precedence ?

I would be happy to get answers for this 

 

 

Accepted Solutions (0)

Answers (1)

Answers (1)

yasmin_alayyan
Advisor
Advisor
0 Kudos

Hello rahulakshay

The strategy profile maintenance is done at transaction /SPRO (customizing).

Then the menu expansion depends on the SAP product version. But usually this is the path:

2024-05-08_17-09-53.png

Click in the 'clock' button to run it, then you can create new entries or copy existing ones.

When working with user-specific profiles, you enter a Customizing ID in the profile maintenance. If you are working with general profiles, you leave this empty.

If you want to perform scheduling using your own user-specific settings, you should create profiles with your user name in profile maintenance as a Customizing ID. (The user name is the name with which you log on to the system).

The system automatically uses the user-specific profiles - if they exist - in the product planning board and order view (otherwise, it uses the general profiles). You can specify any profiles you want if you call up the detailed scheduling planning board directly.

This is described in the F1 help from the system.

 

Best regards

Yasmin

SAP Support