on 07-17-2021 6:21 AM
Normally we use PS for capex budget monitoring and control. Please guide me if we can use it for revenue monitoring
1.At wbs level, We will assign the budget and same wbs will be used in sales order for actual revenue. Budget control should happen for revenue account as well.
Eg. Suppose i have assigned budget for 1000 USD against WBS and now,system should not allow to book sales invoice more than 1000. Similarly I can do transfer the remaining budget between WBS to WBS.
Standard report should get updated same like S_ALR_87013558. Report should say Budget,Actual revenue, remaining budget. Only remaining budget should be transferred.
Hi Yogendra,
Why invoice amount should not exceed budgeted amount?
Would you please explain the business reason for your scenario?
Thanks
Regards
Srinivasan Desingh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
9 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.