S4H - the transfer of simulation version into the active one creates no secondary requirements

ws
Explorer
0 Kudos

Hi,

once we are done with the simulation version, we transfer the results into the active one. There we see that now and then the quantities are not copied 1:1 or in general no secondary requirements are generated for the components.

what can be the reason?

have a good day!

Walter

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

If you want to have PIRs generated to the components, you need to assign a planning strategy for subassembly planning (like 70) to those components. 

Regards,
Caetano 

ws
Explorer
0 Kudos
Hi Caetano,
ws
Explorer
0 Kudos
Hi Caetano, I was expecting the following when we copy the planned orders from the simulation version: the planned orders will be copied 1:1 and hence they will create secondary demand for the components. But very often I see that planned orders are copied but no secondary demand is created for the components
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos
Are you talking about pMRP or LTP?
ws
Explorer
0 Kudos
it's about LTP