define a purchased order as a requirement in MRP

Kobra
Discoverer

Hi, How do I define a purchased order as a requirement in MRP, and after running MRP, how do I get a planned order in the production company?

Accepted Solutions (1)

Accepted Solutions (1)

alizamani
Participant

Hi kobra

To define a purchase order as a requirement in Material Requirements Planning (MRP) and get a planned order in the production company in SAP, you need to follow a series of steps. Here’s a detailed guide:

Step 1: Define the Purchase Order as a Requirement

  1. Create a Purchase Requisition:

    • Transaction code: ME51N
    • Fill in the necessary details such as material, quantity, delivery date, plant, and purchasing group.
    • Save the purchase requisition.
  2. Convert Purchase Requisition to Purchase Order:

    • Transaction code: ME21N
    • Enter the purchase requisition number and convert it to a purchase order.
    • Ensure the purchase order is completed and saved.

Step 2: Configure MRP to Consider the Purchase Order

  1. Maintain Material Master Data:

    • Transaction code: MM02
    • Enter the material number.
    • Go to the MRP views (MRP 1, MRP 2, MRP 3, MRP 4).
    • Ensure the MRP Type is set to PD (MRP).
    • Set the appropriate Lot Sizing Procedure and other relevant MRP parameters.
    • Save the changes.
  2. Maintain MRP Control Parameters:

    • Transaction code: MD02 (for single item, single level) or MD01 (for total planning).
    • Enter the material and plant.
    • Set the appropriate planning parameters like processing key (e.g., NETCH for net change planning).

Step 3: Running MRP

  1. Execute MRP Run:
    • Transaction code: MD01 (for total planning) or MD02 (for single-item, single-level planning).
    • Enter the necessary parameters like plant, MRP controller, and planning horizon.
    • Execute the MRP run.

Step 4: Review Planned Orders

  1. Check Planned Orders:

    • Transaction code: MD04 (Stock/Requirements List).
    • Enter the material and plant.
    • Review the planned orders generated by MRP. You should see planned orders if there are requirements (such as dependent requirements from a purchase order).
  2. Convert Planned Orders to Production Orders (if needed):

    • Transaction code: MD15 (Collective Conversion of Planned Orders).
    • Select the planned orders you want to convert.
    • Convert the selected planned orders into production orders.

Important Points to Note

  • Integration: Ensure that the integration between MRP and purchasing is correctly configured so that purchase orders and requisitions are considered during the MRP run.
  • Master Data Accuracy: Accurate master data (material master, BOM, routing) is crucial for MRP to generate correct planned orders.
  • MRP Type: The MRP type in the material master should be set to a type that allows for planning (e.g., PD).
  • MRP Parameters: Ensure that the MRP parameters (such as lot size, safety stock, reorder point) are appropriately set.
    I hope it will be noticed