Dear Experts,

Following is our scenario and requirement.

we have a Parent Jobchain ( JC_Parent) and a 3 chield job chain.

JC_Parent has a wait event.

If the wait event is not raised for 5 mins after schedule , then JC_Parent needs to be skipped/ignored and then next jobs in schedule should continue.

If you have any idea on this , please share.

Thanks,
Ruban.S

Accepted Solutions (0)

Answers (1)

Answers (1)

gmblom
Active Contributor

You can put a time window with overdue after 5 minutes to cancel the chain with the event on it