Hi Team

Here is our scenario , we have already upgraded SAP EPC component to 3.2 version in SAP PO/NetWeaver SP11 , both directions the data flow was flowing using SAP EPC Primavera API Adaptor.

SAP R/3<-> SAP NetWeaver SP11 <--> Oracle - Primavera P6 (19.20 version).

But when we upgraded to SAP PO/NetWeaver SP27 , we see an issue .

Integration between SAP R/3 and P6 is only working one-way : SAP to P6 is not working , where as P6 to SAP working.

We really don't understand want went wrong?

As per the PAM , we see the SAP PO/NetWeaver SP12 Onwards , EPC connector is supported.

https://support.sap.com/content/dam/launchpad/en_us/pam/pam-essentials/EPC30_PAM.pdf

we wen through couple of notes , but nothing helped us , Connections are showing success , no errors in the NWA logs

2486928 - SAP EPC Primavera P6 EPPM configuration using Primavera P6 EPPM Integration API: setup/settings/troubleshooting - SAP for Me

2297855 - SAP EPC Primavera P6 EPPM Integration: setup/settings/troubleshooting - SAP for Me

Please let us know , what are we missing or done wrong here?

Thanks

Sai

Sriram2009
Active Contributor
0 Kudos

Hi Sai,

Could you share the version details of SAP R/3 and SAP PO NetWeaver along with SP level?

Regards

SS

JosipMatun
Explorer
0 Kudos

Hello Sai,

Have you checked the EPC logs? If Netweaver is installed on the Linux usual file path is: /usr/sap/YourEPC Solution/logs. If no logs currently exists, it means they are not enabled. You can enable them in the EPC configuration wizard.

By the scenario you described, seems that writing data to P6 fails, but the read is ok.

In any case, some error or empty data should be seen in the EPC logs.

Regards,

Josip

Accepted Solutions (0)