Remove triangle's from the resource chart which represent finished operations in DS planning Board

SAPSupport
Employee
Employee
0 Kudos

User is getting triangle's in the resource chart which represent finished operations for the past period in DS planning Board.

They want to remove it because they still see whether there are still open operations not finished yet by production

## Keywords: triangle, confirmed operation, partially confirmed operation, finished, /SAPAPO/CDPS0, DS planning board, Planning Board ##


------------------------------------------------------------------------------------------------------------------------------------------------
Learn more about the SAP Support user and program here.

Accepted Solutions (1)

Accepted Solutions (1)

SAPSupport
Employee
Employee
0 Kudos

The transaction /SAPAPO/CDPS0 displays different objects, depending on the settings of each chart. The resources chart can displays activities of the operations even when the manufacturing orders are final confirmed.

For a final confirmation, for example, the predefined is a triangle pointing downwards.

Note that zero duration orders, usually final confirmed, are presented with a triangle and a thin vertical line in the resource chart. And, depending on the order duration, the line may be hidden by the Final Confirmation icon, and then just the triangle may be shown.

This behavior (the adoption of a triangle in the graphical object) is expected and is hard coded - therefore, cannot be changed.

To avoid this situation, the order must be either technically completed (TECO) in S/4HANA or ERP; or deleted.