Totals Bar in planning Row

0 Kudos

Hi. Can anyone suggest an ad-hoc graphic element type that would display the 'sumbar'.

I refer to MRS conf guide 2013_SP39

Procedure To be able to use the totals bar in the planning row, you have to make the following Customizing settings:

1. Activate the totals bars function for your UI profile in Customizing for SAP Multiresource Scheduling under Set Up Scheduler Workplace Workplace Profiles Define User Interface Profiles Views. Select the Disp Sumbars checkbox to do so.

2. You can specify a graphical element for the totals bars of your UI profile in Customizing for SAP Multiresource Scheduling under Set Up Scheduler Workplace Workplace Profiles Define User Interface Profiles Other Graphical Elements of Planning Board.

3. In Customizing for SAP Multiresource Scheduling, under Set Up Scheduler Workplace Define Settings for Totals Bar, you can specify whether the system displays all the capacitive assignments for a resource in one totals bar or whether each capacitive assignment belonging to the resource is displayed in a separate section. You can also specify whether the totals bar is to change colour at a certain time (for example, 24 hours before the end of a capacitive assignment).

Customizing settings do not provide an example and I cannot make it work

I understand that either we use standard graphic profile : MRSS_SO_BAR either we have to build a new one like ZMRS_SO_BAR.

Still I struggle to make it work. Help on points #2 & #3 would be appreciated.

Thanks anyway and good luck for those facing same issue.

0 Kudos

Forgot to mention we are using MRS 900 ERP ECC6 mode (not Netweaver)