Dear SAP MII Expert,

I would like to know about your kind experiance for KPI and dashboards on historical data at least 1 to 3 years for OEE along with downtimes in S/4Hana and Manufacturing Integration Intelligence as currently we have only shift wise dashboard available in standard OEE MII.

We have only MII, SAC along with S/4Hana onpremise solution in scope. MES is not part of scope. In our case, may retention time is from 6 month to 12 months in MII depend on hardware sizing.

Production related plan and actual quantities may available in S/4Hana in form of Production Order , Material Movement (261, 101 mvt. etc. can be reported back to ERP) and Order Confirmation (Yields, Rework and Scrap can be reported back to ERP from OEE) but some data is belonged to MII like production order start and end counter by machine/ work center, machine speed, schedule, unschedule downtimes, change over, flow time along with reasons codes.

1. So can we make this OEE type of data also available in S/4Hana for our historical analysis?

2. If yes, then can you please suggest how we can make it available in S/4Hana for our machine (machines, work centers, groups, plants and globally) related periodically (shift, daily, weekly, monthly, quartly and yearly) performance KPI and Dashboards by considering above scope?

3. We have designed global (One) and plant (Two) hierarchy with 50 machines and we want to save our machine specific data (start and end counter and total counter, machine speed) on the basis of plant hierarchy and production order wise in MII so please guide how to meet this requirement.

We want to save downtime on the basis of actual existance (manually from OEE MII dashboard or can be directly from machine integration) and machine related other data (order start and end counter and total counter, machine speed) needs to be save hourly basis and also when order start and end and when shift start and end.

Your support will be highly appreciated

Regards/ Nasir Ramzan

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

I am facing the issue, My requirement is to get and save real-time MII Counter and machine speed (fetched from Plant connectivity) data by production order and plant hierarchy. Kindly suggest how it will be possible.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

I suggest you to consider the Digital Manufacturing Cloud solution for insights about your manufacturing KPIs:

https://www.sap.com/assetdetail/2020/05/4adb8a34-987d-0010-87a3-c30de2ffd8ff.html

Regards,