Hi Experts,

I have created 2 cost sheets for 2 processes in SPRO.

The first process for a semi finished product which consumes raw material with one activity and one overhead as structure.

And in the second process for another product which will consume the semifinished product created in the first process, with no activities but 3 over heads.

I have created 2 cost centres for two process.

Production version and workcentres created for these two process.

But while checking the output in CK11N in the first process, Activity is appearing but regarding overhead instead of one overhead of first process 3 overheads of second process are appearing.

Please reply for further clarifications too.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Bhanu Prakash,

Kindly check the cost sheet assigned in Transaction OKKN.

Regards