Work Order for each shifts (3 Work Orders in a day)

sp0123
Participant
0 Kudos

Dear Expert,

There is a requirement to generate Planned Work Orders for each shift everyday i.e. 3 Work Orders in a day.

Can you provide some insights on how to map this process in the System

PS- I have a solution in mind. Create 3 Plans (Shift A, B and C) and schedule them. I am looking for some more ideas for effectively mapping it.

Thanks and Regards,

S. Kumar

Accepted Solutions (0)

Answers (2)

Answers (2)

preetirai1984
Participant
0 Kudos

Hello Kumar,

You can add as a number of operations as many you want. Maintain relationship FS between operations where operations are for different shifts and operations falling on same shift relationship SS.

preetirai1984
Participant
0 Kudos

Hi,

You can create one maintenance plan and task list with three operations where operations 1, 2 and 3 will have FS relationship with each other and duration=8, considering no of person=1. This one work order will come with three operations where one operation for each shift. With this, you can save the work order number range too.

sp0123
Participant
0 Kudos

Thanks a lot for the answer.

This would definitely save on WO number range.

In our case, there are multiple operations for one shift.