cancel
Showing results for 
Search instead for 
Did you mean: 

Viewing of WBS elements

0022267830
Explorer
0 Kudos

In a running project when we try to view the WBS elements, all the WBS elements are showing from 1st WBS till the Last and viewing them is really difficult it would be of really helpful if either have a filter, sort or a search criteria to view these WBS for projects which are really having WBS element more that 20 and close to 100 is very difficult to view.

Regards

Venkata 

Accepted Solutions (1)

Accepted Solutions (1)

Feras_Al-Basha
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi 0022267830 ,

Thank you for sharing. I am assuming you are referring to customer & internal professional services projects (J11/1A8) and specifically to the apps like "plan customer projects" or "plan internal projects."

These apps contain information from multiple data sources and for performance purposes the guideline suggested is to keep projects created under 100 work-packages to facilitate the use of these apps.

By default the central page in the projects apps populate a subset of the work-packages and will load the remaining list of work-packages when the user clicks on "load more." As you mentioned to handle projects with more than 100 work-packages more robust filtering capability would lead to a more user-friendly experience. Therefore, I suggest you raise a customer influence request or consider side-by-side extensibility options to address your requirements.

I hope this helps.

Best regards,

Feras

0022267830
Explorer
0 Kudos

Hi

We have raised an influence ticket thank you.

Regards

Venkata

Answers (0)