on 12-11-2023 3:07 PM
Hello,
we would like to use time event confirmations for process orders with transaction CORZ.
Our master recipe has one operation with two phases:
On the calculation tab of the resource are six activities:
I assigned the recording type group "Processing" to the activities 3 and 4.
The recording type group "Setup" is also available. But it is not taken into account in transaction CORZ. So I didn´t assignt this recording type.
The activities 3 and 4 can be calculated automatically with time event confirmations.
Regarding the other acitivities I I would like to ask the following questions.
Thank you in advance.
Best regards
Julian
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.