Hi Team,
We are Working on the Professional Services Time and Expense Scenario.
We created plan customer project with time and expense, the we add the resource with planned cost and Planned Revenue ,confirmed the resource.
Go to manage my time sheet and enter the time sheet with required Project.
Go to Manage project billing and select the Project billing ,but we unable get the to bill amount and getting error in creating the Project billing request.
System is giving below error message.
One or several postings were excluded due to incomplete configuration.One or several postings were excluded due to incomplete configuration.
Regards,
Naveen Phani
Hi Naveen,
Can you please refer to the KBA 3088151 - Manage Project Billing gives warning "One or several postings were excluded due to incompl...." to resolve the issue.
Thanks,
Monisha.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.