Hi, I have got following qs:
Which status is required in the SAP standard so that network activities receive a progress value in the progress analysis?
Which status is required in the SAP standard so that WBS elements receive a progress value in the progress analysis?
I am using measurement method 0-100
Many thanks in advance!
All PS objects must be released REL in order to accept charges.