Hi Experts ,
I have a case where the SO is created for a KMAT material and PR is generated from the scheduled line . When i save the SO , automatically Source is getting assigned to PR . But the strange thing is that for some of the Cases , Source is not getting assigned , only Porg is getting assigned in the PR .
( even though the scenario is same i.e Material , org element , PIR ) . I need your help in finding out the Root cause of this unusual behavior .
Thanks
Hi,
As you clearly said that no source list maintained for the Material and Plant Combination, then contract must be created for that material with plant where you have vendor with other details in contract. When you save the SO , automatically PR created and Source is getting assigned ,which triggers from valid contract.
Regards,
Biju K.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Biju ,
Thanks for your reply .
PIR is already there for the material / plant / porg . strange thing is that in some cases source is getting assigned correctly when the SO is saved but there are some cases when the SO is saved , only Porg is getting assigned to PR (No vendor and PIR assignment) . I just noticed that it is only happening for one user . Other users are not having issues . Can you tell any user specific settings missing ?
Thanks
Check source list assignments for those material plant combinations.
Also check the validity periods.
Regards,
Dakshesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
7 | |
7 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.