Scheduling agreement Release strategy release indicator

Former Member
0 Kudos

Hi all

For the Scheduling aggreement Release strategy is present & release indicator is 6 , Now the requirement is whenever user is changing the any value Scheduling agrrement it should go for rerelease. for any minor change in value even the value lies between the same Release strategy

Release strategy is configured on Purchase group & Value character

Also what is the difference between release indicator 4 & 6. for any changes in the SLA release strategy will be reset in this two release indicator.

Thanks & Regards,

Rajesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

This is a standard phenomena any change in value (increase)will reset the release stategy

and indicator 4 & 6 are same only in case od indicator 6 if you have taken the oout also it will get affected