Hello,I'm working on SAP ECC 6 version and I'm looking for a way to get a report showing :
maintenance plan - item - task list - components linked to the current task list
Does anyone have a way to do that ?
thanks
Best regards
Hello,
I used SQVI and logic database to do it
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello thanks for answer.
yes tried but no way to fullfill the maintenance plan number in IA10 and IA17.
best regards
Roméo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Have you try IA10 and IA17?
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
9 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.