cancel
Showing results for 
Search instead for 
Did you mean: 

How to Trace Cost center Analysis Period Versions in HANA ?

former_member183378
Active Contributor
0 Kudos

As per the Business requirement, we are interfacing CC hierarchy information along with Master data into another third system using by our client for reporting purpose. But here we are facing issue to track the cost center versions with analysis period details in HANA.

For E.g:- Cost center A is having different periods

1. CC A with 01.01.1990 - 30.06.1995

2. From 01.07.1995 - 31.12.2010

3. 01.01.2011 - 31.12.9999

But we could find this info in T code - KS03 / KS02 level. Do we have any table or program to track the same like to pull logic in order to interface data to 3rd party system ?

Your inputs would be highly helpful for us.

Thanks & Regards,

Lakshmi S

View Entire Topic
iklovski
Active Contributor
0 Kudos

Hi,

This data is stored in CSKS table.

Regards,

Eli

former_member183378
Active Contributor
0 Kudos
Hi Eli,

Thanks for your reply.

I haven't find different versions of analysis period details of a particular cost center in CSKS Table. Hence kindly share how to track this at table level. Please help me once.

Best Regards,

Lakshmi S

T

iklovski
Active Contributor
0 Kudos

If cost centre is defined in different periods, it should be visible in CSKS. If it's not visible there, it means that there is just one period defined for cost centre