What could be the cause of a handfull of remaining balances on Funds Reservations (containing WBS elements)that have been closed using FMMC to still show in Project Systems report S_ALR_87013532 (Plan/Actual/Variance).

For example, we have one scenario whereby and funds reservation was created for $3,050 in FY06. Invoices in FY06 totaling $3,045 were processed against the reservation leaving $5 open.

At fiscal year 06 end it was determined that the reservation should be closed using FMMC and it was closed. For some reason the $5 is still showing in Project Systems on reports under the encumbered section.

Any ideas? I have been trying to duplicate the issue. In DEV, if I close a reservation with a WBS element using FMMC, Project Systems gets updated immediately. Most reservation closings have been fine, its just about 20 over the past fiscal years that have ended like this.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Resolved