on 03-09-2024 8:01 AM
Good Day All,
We have to close or partially received service POs driven from project systems. we release strategy implemented on our service POs.
Regards,
SMA
Hi,
There are 2 options I could suggest:
1. Create a new SES with empty service lines and flag as delivery complete indicator and save. This will close the PO.
2. Flag the delivery complete indicator manually for the PO - refer the note # 2634029 - How to close a service PO
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
it is not possible to close a service PO with a delivery completed indicator . you can only lock or delete the line to remove any commitment that may still exist on the PO. You may try thru MEMASSPO txn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think you mean it is a purchase order created from a PR originated in Project. You can lock the PO line item in case of service PO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.