Hello,
I have requirement where we have more than one production version for FERT and HALB. Let's say there are production versions A and B for FERT and production versions A and B for HALB.
During the creation of a plan cost estimate in transaction CK11N the user can select the production version for FERT. Now the requirement is that if the selected production version for FERT is A then the version for HALB should also be A. Meaning if the cost estimate for FERT is planned for line A then the cost estimate for HALB should also be planned for line A.