on 06-11-2013 10:29 AM
Hi experts.
Im new with CS module and stuck with problem to update actual costs for CS order through BAPI. I were look around and found some helped post and here is my process:
1. create notification (through tcode iw54 or iw51).
2. create service order (dircect from notification then edit it with tcode iw32)
3. assign operation, components....
My requirement are retreive corressponding data to show and technical could do confirmation through his pocket PC. Im using bapi BAPI_ALM_CONF_CREATE to do this requirement but i couldn't update actual costs for that order even I can manually do it in tcode iw41.Here is my questions:
1. Some one told that we need tick backflushing indicator under general data tab of component, i did it but nothing change, I dont know if i miss anything here.
2. Incase backflush is only option and could work so with order that does not have component how can we update actual costs?
3. After finish all operations, do goods movements by backflush, acutal costs updated too how can I close that order ( system status = CLSD) using BAPI? I find out BAPI K099_PM_ORD_STATUS_ABGS_SET but dont know how to use it.
Please kindly help me out, some piece of sample code would be helpfull, sorry for a noob question and not good english.
Thanks and regard.
As per my understanding based on your query, actual cost is not getting calculated either through BAPI or manual confirmation.
If it is so, please check the following.
If possible, attach all above 3 screen shots for our reference.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think it is not problem with the Activity types passing to BAPI, since Planned cost already calculated
and in your second screen attached, i don't see any Status for Confirmation or Goods movement
does the BAPI is used for confirmation and goods movement as well?
please try to confirm the operations and goods movement manually at first place, if the actual cost is being posted then it could be issue with the BAPI which you have to debugg and see
just for your information
try to manually confirm the operations in IW41
and goods movement from IW41 as you already set Backflusing indicator
try and revert
regards,
santosh
Hi,
The Activity type need to be maintained in the work center, which will auto populate in the workorder to calculate the planned cost.
Maintain the Activity type in the Costing tab of the workcenter used in the workorder.
Thanks
Mani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
All values should be captured for manual processing same mandatory and Default values should be Populated in BAPI.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.