Hi Experts,
I have a question regarding preventive maintenance, I need to generate two Maintenance order for a task list one in the morning and another one in the afternoon, how can I manage this request ? I have a maintenance strategy but I think I can't include "Half day" in the package,
Thank you for your help,
Regards,
Mika,
Create both orders in the morning, but put a different description in the maintenance item description e.g. "Morning maintenance" and " Afternoon maintenance".
PeteA