on 07-02-2013 7:23 AM
Hello,
While converting planned order into production order, system won't reread BOM but bring all the component data from planned
order to production order. However, I saw different system behavior in release 605 and 606. The scenario is that I changed the component
qty or component in planned order and then convert that planned order into production order. But I found that production order
didn't bring in that changed component data but have BOM reexploded. I know it's possible to have BOM re-copied from t-code
COHV for converting planned order into production order. However, I converted the planned order from stock/req. list. I have
searched notes but no program error notes were found. Can anyone advise me what's up with this system behavior?Thanks.
B. Regards,
Nancy
Dear Nancy,
Apart from the Brahmankar advise, please post to SAP as there may be a bug for 606 version .
Regards,
Subrahmanyam B
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Please refer OSS note 391846 - Modif: Reading master data when converting planned order
I hope it will solve this issue. Modification in note is applicable for all version.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
9 | |
7 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.