on 10-18-2020 7:33 PM
Hi Guys,
I am running MRP with MD50 and the schedule is "Lead time scheduling and Capacity planning"
after running MRP the Planned order component requirement date is after end date of the planned order
For Ex: Order start date is 03.11.2020 and order end date is 03.11.2020 and the component requirement date is 04.11.2020 (you can observe in screen shot)
Note: in our business process in-house production time is 0 days
Waiting for your valuable suggistion
Thanks and Regards
Chengalrayulu Koppala
Hello
Sometimes, when there is a difference between the in-house processing time and the times defined in the routing, you may observe this kind of difference. It happens because system will first calculate the order dates with the in-house processing time, then run lead-time scheduling to calculate the production dates. When there is a difference between those times, the basic dates may be adjusted to match the production dates, causing this issue. I would suggest you to run transaction CA97N to update the in-house production time with the routing information and then run MRP again for this material.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Check if you have a lead time offset for your component in the BOM.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
9 | |
6 | |
6 | |
5 | |
5 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.