Planned delivery time in purchase requisition

0 Kudos

Good morning everyone,

For some time I have been trying to figure out where ECC gets the planned delivery time in the purchase requisition from. In my example, it's 11 days. I have checked the system and see the following

MM03 of the material => 14 days

Purchase info record of the material => 7 days

Transport lane for the material => 168 hours (7 calender days)

Source list (ME03) => empty

Where else can the system look for planned delivery dates?

Thanks

Wes

Accepted Solutions (0)

Answers (2)

Answers (2)

ankurch
Active Contributor

Hi Wes,

System calculated Planned delivery time by Function Module "FRE_PLIFZ_CALC_MARC", here system check the entry of MARC subtracted by last GI date.

Thanks,

BijayKumarBarik
Active Contributor
0 Kudos

What about purchase agreement(Contract)