on 09-23-2022 7:28 PM
To produce FG1 - I00 EA need a component C1 =50 EA C2=100 EA. I know scarp can be there, hence I have put assembly scrap % as 10%. Now my process order FG1 quantity would be 110 and C1= 55 & C2 =110.
Question
1)What would be the planned cost of material ? Cost of C1=55 C2= 110 qty or for cost of C1=50 + C2=100 ?
2)If the planned cost = C1-55 and C2-110 , is there a way I can have planned costs in 2 GLs? one gL shows planned cost for C1-50 + C1-100, and the second planned cost GL shows C1-5 C2-10.
3)I want a feature where by I can have planned cost break up -real planned cost + scrap planned cost and actual cost - real stock (GR) cost and real cost of scrap cost
4) I will do GR for 100 and balance 5 GR should be for scrap account- How can I achieve this?
Your last question— In UD you have the option to specify, how which will go to unrestricted from quality stock and how much will go to scrap
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
9 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.