on 06-25-2023 7:34 AM
Dear
I have two question about the billing plan.
1I 1. I want to have a fixed date, 25th of each month as billing date. So I was changed the days in month to 25 as below. but it’s not work in system. But it's not work.
2. User want to skip the public holiday for billing date. I also put the calendar in Date rule. it's also not work
Could you please guide how to fulfill the requirement for both requests. thanks
Hello neeraj.jain16,
Thanks for your answer.
The issue is for R3 instead of CRM system.
It's not related to the billing value calculation. it's related to the billing date determination.
Please check if any idea of this request.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello yyhemon,
Please refer below SAP Note. Hope it's clarifies your query.
https://userapps.support.sap.com/sap/support/knowledge/en/1614065
1614065 - Billing value not calculated correctly on item level when using periodic billing in service contract
Confirm if it's works for you.
Regards,
Neeraj Jain
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
10 | |
5 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.