on 09-22-2023 7:09 AM
Hi Experts,
I have a business requirement to do the following. I'm still a bit new to MRP and Capacity planning.
The company has 12 manufacturing plants and a centralized procurement department. Some materials are shared between plants. The procurement team is requesting a way to create a monthly PR based on the results of the MRP run.
As a solution, I have tried using the Individual/Collective indication in the MRP views but I have no luck. I tried using Monthly Lot sizing Procedure (MB) as well both alone and with the changes in MRP 4 and still no luck.
I still keep getting multiple PRs for each month as shown below:
Have I made an error somewhere?
Client Version: SAP S/4HANA 2022
Reagards,
Dexter
Hi Ajit,
Thank you for your response. I maintain PIRs and the strategy group 40 in the header materials.
Below is an extract from my MD04
As you can see I have 2 PR created for the same date. What can I do to correct this? I used the pegged requirement report MD09 and I get no result for the PR 10007423, but I get a detailed list of items for the PR 10007424.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
From where are your requirements coming from? If you use strategy 40 and maintain Plan independent requirements for the header material, i think you will be able to get monthly Plan order or PR for the PIR quantity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
8 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.