How to transport request created on quality to production?

miske
Participant
0 Kudos

Hello everyone, 
I want to transport some standard text that I created on so10 in quality. Directly in Quality I created new workbench request in SE09, made subrequest type Development/Correction. Via program RSTXTRAN I selected all the standard texts that I want to transfer and put all of them into the subrequest.
Went back to SE09, released the subrequest and then the main one. But when I got to production in STMS I do not see that request anywhere. 

Can someone explain to me what am I doing wrong, and how to import this request into produciton?


P.S.
Since those standard texts where initially made on quality (not development) I tried to transport the directly from Quality to production. 