Dependent Requirements is not getting rounded off for unit EA in MD02/MD04

mohanramkmd
Explorer
0 Kudos

I am analyzing an issue where the user has asked to check why the dependent requirements are not getting rounded off to the nearest integer (UOM - EA). I am an ABAPer but very new to MRP and don't know anything about it. I suggested 1 BADI which we can use to change the parameters while displaying but the functional has asked to find the logic for how the quantities are rounded for PR & PO but not dependent requirements. Please let me know if there is any functional workaround for the issue. I have attached MD04 & MM03 screenshots, please suggest me something.