on 04-17-2019 7:51 AM
Hello All,
In the production order, after doing changes in BOM or in Master Recipie, the planner have to execute the Read Master Data option so the components and quantities will be refreshed.
How can I get any change log for this operation on a known production order number or range of orders in particular date and range of hours.
I need to know if read master data have been done on particular production order (created in cor1 for example), when and by whom.
Kind Regards,
Amit Berku
Hello
As per Standard SAP, only Explosion date add to Table AFKO
You can built Z Table for the history of Explosion date value changed in Table AFKO field AUFLD
Take help from ABAP Consultant
Regards,
Muhamed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
9 | |
7 | |
6 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.