Dear Team,

Facing issues while creation of migo

A project estimate is created within the budgeted amount and after approval network is released when the utilization of migo with ( mov type -281) "gives error -- the item 002 network 5429614 0010 budget exceeded " is showing even sufficient balance available and approved cost is also increased now

seen all the reports budget is available in the wbs , please help me in solving this issue

Accepted Solutions (0)

Answers (1)

Answers (1)

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

Check you budget assignment over the WBS structure and over time. You are trying to post actual cost over the assigned budget amount. Assigned budget is separate from plan costs.