Hi All, 

Is there still an opportunity to collect costs for an internal asset investment project on WBS elements in S/4 HANA Public Cloud?  Something like the functionalities in modul PS.

Thank you in advance.

Best regards 

Christian

Accepted Solutions (1)

Accepted Solutions (1)

riwamouawad
Advisor
Advisor
0 Kudos

Hi ckretsch

Investment Projects are covered in the 1NT test script: https://rapid.sap.com/bp/#/browse/scopeitems/1NT

When using investment projects an AUC is created which holds the costs of the projects until the settlement is executed.

Investment projects profile is used in Capital Investment scenarios with the purpose of supporting companies to manage and control the enterprise-wide project related investments. Capital Investment projects are used to capture the costs of assets under construction (AuC) during the construction phase and create the final asset once this phase is completed. Although the AUC is what will hold the costs, you are able to report on the WBS element using the different project cost reports and seeing which GL accounts are posted to.

Hope this helps!