hi Specialists, is there any solution on how ot manage the Version management in Contract (scheduling agreement)?
because as per note "1046794 - FAQ: BAPI for Outline Agreement " it's not possible:
"11. Question:
When an outline agreement is changed via BAPI, system does not create version data, even if Version Management is activated. Why?
Answer:
Version Management is not supported in the outline agreement BAPIs. This is a missing functionality. The workaround is to change the document in ME32K or ME32L.
"
is there any one that were able to find a trick on this issue?
thanks
Hello ahalim
I don't think there is any simple trick here. If there was, SAP would have implemented version management in BAPIs long time ago.
In my opinion your best bet is to use old and proven batch input call to either ME32K or ME32L.
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.