02-14-2007 1:09 AM
i need to change this program based on my requirement , but i don't know the logic of this program ,there are some puzzles about the logic of the program. the requirement is that: when create the batchjob, the number of the batchjob is fixed , and the steps of the batchjob is also need to fixed, but the per step that contain the number of the customer is dynamicly. how to do it .i need to fix the step of the batchjob ,how to do it ?
it is very emergency . who can give me some useful suggestion?
Thanks in advance.
10-29-2007 1:54 PM
Hello, Ming.
I'm not sure whether this will solve your problem, but check OSS note 652219. It describes an adjustment to the SDBILLDL program so that you can schedule it directly in background instead of it being "spawned" by the RV60SBAT program. That way, it can be a "fixed" scheduled job.
Hope this helps!
Cheers,
Des.