I am getting above error in 'BAPI_PO_CHANGE'. I searched in different notes but unable to get correct answer.
How can I change Delivery indicator of released PO.
I tried 'BAPI_PO_CHANGE' and in that wa_poitemx-no_more_gr = 'X'.
But still I am getting 'Purchasing document has release indicator R (changes not possible)'.
Kindly tell me alternative way.
Thank you.
08-31-2015 2:52 PM
Hi,
First of all check manually in ME22N that are you able to change the PO release strategy for R (Release) to Unreleased or not. if you are able, to change then we check from BAPI side or not.
may be some enhancement or configuration restrict to being a unreleased PO with respect to release strategy.
I hope some API are their which help you to rest the release strategy.