Hi,
Let me know the link b/w cost center and order number?
Regards
11-02-2007 2:27 PM
11-02-2007 2:29 PM
Hi,
(<b>on behalf of rajareddy</b>)
The Service order <b>aufnr</b>(Order Number) in iw32 tcode.
Regards
Message was edited by:
Kiran Sure(skk)
11-02-2007 2:41 PM
The order has operations assigned to it, which have work centers assigned to them. The work center is assigned to a cost center.
use aufnr to access afko to get aufpl
use aufpl to access afvc to get arbid for the oeprations
use arbid (workcenter) to access CRCO to get cost center assignment
This will give you the cost center where the work is done.