How to Change Scheduling Agreement Schedule line data thru BAPI ??

Former Member
0 Kudos

Hii

I want to change the shedule line data for a scheduling agreement .

I used BAPI_PO_CHANGE but as this BAPI is used for PO only this gives a

Error Message for Scheduling agreement .

Please suggest me BAPI or FM to update the Scheduling agreement Schedule line.

Regards

Ajitabh Pradhhan

3 REPLIES 3

graghavendra_sharma
Contributor
0 Kudos

Hi

Try out this BAPI

BAPI_AGREEMENT_MAINTAIN

0 Kudos

Hii Raghav

My SAP version is 4.6C i dont think this BAPI is present in this version.

Regards

Gaurav

Former Member
0 Kudos

as BAPI_AGREEMENT_MAINTAIN is not available in 4.6c

Please help me out on hwo to maintain Scheduling Agreements .

Regards

Gaurav