07-05-2007 10:53 AM
Hello all,
Is there exists any functional module with which I can know whether a background job has ran successfully?
Thanks and Regards, Pradeep
07-05-2007 10:59 AM
Hi,
If you go to se37 and type in jobread* you'll probably find some function module.
Maybe BP_JOB_READ works for you.
Kind regards, Rob Dielemans
07-05-2007 10:59 AM
Hi,
If you go to se37 and type in jobread* you'll probably find some function module.
Maybe BP_JOB_READ works for you.
Kind regards, Rob Dielemans
07-05-2007 11:00 AM
Hi
try using the FM
TT_BACKGROUND_JOB_FINISHED
Pass the values
Import parameters Value
JOBNAME
USERNAME
regards
Shiva
07-05-2007 11:01 AM
Hi
check the following related to JOB
BP_AL_ABORTED_JOB_REP
BP_CALCULATE_NEXT_JOB_STARTS
BP_CHANGE_JOB_STEP
BP_DELETE_JOB_STEP
BP_FIND_JOBS_WITH_PROGRAM
BP_INSERT_JOB_STEP
BP_IS_JOB_ACTIVE_IN_WP
BP_JOBLIST_PROCESSOR
BP_JOBLIST_PROCESSOR_SM37B
BP_JOBLIST_STATUS_GET
<b>BP_JOBLOG_READ
BP_JOBLOG_SHOW</b>
BP_JOBLOG_SHOW_SM37B
BP_JOBVARIANT_OVERVIEW
BP_JOBVARIANT_SCHEDULE
BP_JOB_ABORT
BP_JOB_ACTIVE
<b>BP_JOB_CHECKSTATE
BP_JOB_CHECKSTATE_SM37B</b>
BP_JOB_CHILDREN_GET
BP_JOB_COPY
BP_JOB_CREATE
BP_JOB_DELETE
BP_JOB_EDITOR
BP_JOB_GET_PREDECESSORS
BP_JOB_GET_SUCCESSORS
BP_JOB_HEADER_MODIFY
<b>BP_JOB_MAINTENANCE</b>
BP_JOB_MAINTENANCE_SM37B
BP_JOB_MAINTENANCE_SM37C
BP_JOB_MANAGEMENT
BP_JOB_MODIFY
BP_JOB_MONI
BP_JOB_MOVE
BP_JOB_PARENT_CHILD_INFO
<b>BP_JOB_READ</b>
BP_JOB_RELEASE
BP_JOB_SELECT
BP_JOB_SELECTION_SWITCH
BP_JOB_SELECT_SM37B
BP_JOB_SELECT_SM37C
<b>BP_JOB_STATUS_GET</b>
BP_OWN_JOB_MAINTENANCE
BP_REMOTE_JOB_SELECT
BP_SET_JOBCLASS_A
BP_SET_WORKFLOW_JOB_STARTDATE
BP_SHOW_ABORTED_JOB
BP_SHOW_JOBLIST
BP_SHOW_JOB_QUEUE
BP_VARIANT_USED_IN_JOB
Reward points for useful Answers
Regards
Anji
07-05-2007 11:03 AM
Hi,
JOB_OPEN
JOB_SUBMIT
JOB_CLOSE
FM BP_JOB_CREATE
Also take a look at the BPJOB function modules in SE37
<b>Reward points</b>
Regards
07-05-2007 11:04 AM
You can check FMs
CATT_BACKGROUND_JOB_FINISHED,
SUBST_CHECK_BATCHJOB and
BDL_READ_JOB_STATUS
also check the field STATUS in table TBTCO , it should be F if the job completed successfully