Activities quantity in table AFRU

Former Member
0 Kudos

Hello gurus,

We have a development requirement, want to get the confirmed activity quantity(such as labor hours) from AFRU.

But i find it very interesting.

If use CO11N to confirm the order, I can find the confirmed activity quantity in AFRU;

If use CO15 to confirm the order, the activity quantity is blank in AFRU.

Also in REM scenario, when i do activity backflush, after i enter the product, production version and quantity, if i directly save it, not do "process activities", the confirmed quantity is blank too.

But both in production order and PCC, I can find the actual cost, means the activities were confirmed successful.

Why? or am i wrong?

Is there another table store the confirmed activity quantity?

Thanks in advance.

Harvey

1 REPLY 1

Former Member
0 Kudos

Hi,

The problem might be the fact that on Co11n you confirm entering time intervals, meaning start time and end time.