on 05-11-2013 6:50 PM
Dear.
I know that status DLV means that goods receipts of production order is completed.
But does exist a similar status for the components , in order to know that goods issue for the
components is completed ?
Thanks.
Hi you can check in,
CO03 ---> Lists -----> Documented goods movement
Movement type (261) will show the goods issue for the header material.
or
Go to MB51 (Material document List) & only give your Production Order No. & execute it to see 261 movement for the sub-components & the GI quantity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You go to Order change mode , go to components/materials tab .In that screen u will get columns like material quantity proposed & quantity withdrawn.
Before confirmation, 'Withdrawn' column will show 'Zero' quantities for all components.
Whenever you do complete 'Confirmation' ,'Withdrawn ' column will get updated accordingly.
Pls. revert if useful.
Regards,
Milind
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.