Is there any way to set the buying of procurement type F materials to a fixed quantity every month?

This should be regardless of on hand stock or demand from a manufacturing material.

Any way to MRP generate PR regardless of the above?

There is contract between supplier and company to buy fixed quantity monthly so it will be regardless of on hand stock or demand.

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor
0 Kudos

Why don't you just create a purchase order for the entire quantity with schedule lines for quantity per month?

Or a schedule agreement. I don't see any need for a contract in that case.