Dear Expert
In a maintenance order How purchase requisition can be triggered for a material if a required material is not available in stock.
Also, Please give your valuable thought on differencce between item catagory L & N. In what cases we have to use L & N in a maintenance order.
Thanks in Advance
In addition to above...
Stock items will create reservation & using MRP, system will generate the PR or PO. For the spare parts, MRP data should be maintained for automatic creation of PR or PO.
Based on the availability check assigned in Spare Parts master, system will check the availability of material in PM Order by which execution or release of PM order can be restricted. Based on the status of components, Item category can be changed from Stock Item (L) to Non Stock Item (N) so that components can be procured outside.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
system is generating PR of "service & repair type". how can I get this PR of material type/spare part PR.Plaease suggest the possibilities.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you put material for non-stock item(N), system will create PR.And u can use this PR in creating in PO (ME21n). by this u can create the PO for the Non stock materail. After this u can check for realising status of PO if it is set u can realse by (ME29n) after this u give GRN for the material which alrady moved to stores and realivetly cost is setteled in settelment rule in order itself.But on stockable item(L) system will create always Reservation no against material quantity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Greetings Pravin,
If your material is not in stock, you will see an unsatisfied requirement for that material in stock. (e.g. t-codes MD04, MD07, CO09). This material then has to be requisitioned (either manually or via MRP) and purchased into stock, then it becomes available and you may issue to order.
An "L" (lager) item is stock material and this will normally be the default item category for Materials that you stock.
An "N" (non-stock item) on the contrary is purchased directly to Order, so it will generate a Purchase Requisition, you then purchase and receive the material directly into Order balance.
Occasionally, you might want to directly purchase a stock material to the Order, you can replace the Item Category when creating the Order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.