production order reservation & availability check???

173 Views

Dear Gurus,

I have a question regarding goods issue of components to production order.

How can I make goods issue of component consider previous reservations

For example,

Material A consists of component B in ratio 1:1

Available quantity of component B is 10 pcs

Production order no. 1000 was created & released with 10 pcs for material A thus generating a reservation of 10 pcs for component B.

Then production order 1001 was created & released with 10 pcs for material A thus creating a reservation with 5 pcs of component B.

I want an error message to be generated if goods issue was done for production order 1001 before 1000 since the reservation of production order 1001 was created after the reservation of production order 1000.