Hello ,

I want to generate a standard PS Report for Dates and Costs ( Planned v/s Actual) based on the Project Type.

Is it possible using standard SAP functionality?

If no, then what can be the work around?

Thanks,

Rohan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Rohan,

Check standard PS report  'CN41 - Structure Overview'

Go to Dynamic selection and select Project type from ' Master Data WBS element '

Enter Project definition and execute the report.

Regards

Tushar

Former Member
0 Kudos

Hi Tushar,

Thanks for the Reply.

Wanted to know if there are say 20 Projects for a given Project Type then is it possible to get the Report using Standard SAP for all the projects under that Project Type

Thanks,

Rohan

Former Member
0 Kudos

Hi Rohan,

Yes, it is possible. Choose the project type(s) through dynamic selection and then for Project definition field, either give the projects in range or give any character from PD along with *.

Regards,

Bala

Former Member
0 Kudos

Hi,

Yes it is possible. Enter Project type under dynamic selection of standard reports. Project type is available in structure reports.

Regards,

Harsh.

Former Member
0 Kudos

Hi Harsh,

Thanks for the inputs.

I got it.

Rohan

Former Member
0 Kudos

Hi Bala,

Thanks for the reply.

I tried the same and it was possible.

Rohan

Former Member
0 Kudos

Hi Rohan,

Yes, it is possible.

Enter 20 projects by entering in multiple selection for a given project type which are selected by choosing dynamic selection as explained above.

Regards

Tushar

Former Member
0 Kudos

Hi Tushar,

Thanks for your reply.

I got it.

Rohan

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hello Rohan,

Have you tried the dynamic selection along with input parameters?

Regards.

Santosh

Former Member
0 Kudos

This message was moderated.