on 05-08-2013 9:59 AM
Hello ,
I want to generate a standard PS Report for Dates and Costs ( Planned v/s Actual) based on the Project Type.
Is it possible using standard SAP functionality?
If no, then what can be the work around?
Thanks,
Rohan
Hi Rohan,
Check standard PS report 'CN41 - Structure Overview'
Go to Dynamic selection and select Project type from ' Master Data WBS element '
Enter Project definition and execute the report.
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Rohan,
Have you tried the dynamic selection along with input parameters?
Regards.
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.