CN33 BOM trasnfer not available for creating STD network

Former Member
0 Kudos

Dear PS experts,

It seems CN33 traxn is only available to load to Projects. If you wish to use CN33 to create material assignment to standard network , it can't be done or am i missing anything.

If customer want Template ready with material assignment ( Do not want to execute CN33 everytime), then i guess you have to do manual assignment in std nework( one time as a part of Master data upload) to make Std network with material assignment.

Best Regards,

Jatin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

CN33 is being used to transfer the material for operative projects. You can not transfer material components to Std Networks. You can assign the material components in Std network activities which are keep calling whenever you are creating operative project from standard template.

Thanks,

Sudhakar

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Jatin,

CN33 is used to replenish an assembly, which has a long replenishment lead time, before the design of the whole product is complete. First, you can transfer this assembly to Project System and generate preliminary requirements. So, this is used only for Operative networks and not for Standard Networks.

Regards,

Bala.