Skip to Content
author's profile photo Former Member
Former Member

Blank Accounting tab in the cProject Simulation

Hello PPM Experts,

I have a cProject created and having 'Transferred' & 'Assigned' status. I.e. the Accounting Structure (with PS Project/WBS elements) for this cproject is created successfully. The Costing data in the accounting tab is also appearing correctly.

However, when I create a 'simulation' for this project, system creates it successfully but with messages " Internal error: Calling costing leads to
exception" and "Costing data may not be up to date".

The 'Accounting' tab of the Simulation do not show anything (i.e. blank tab).

Appreciate if you can try this scenario at your end and share yhr results or provide some inputs to resolve this issue.

Thank you.

Bhushan Sapre

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on May 07, 2013 at 10:04 PM

    Hi,

    Please check whether you have defined adhoc costing scenario in controlling settings. I believe this should solve the issue

    Pramod

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.